Land Warfare: JP2060: healthcare is on the way, slowly | ADM October 2012
The
final phase of JP2060, a project established 16 years ago to deliver a
deployable health capability for the prevention, treatment and evacuation of
ADF casualties incurred in joint operations, is unlikely to go to tender until the
final quarter of 2014.
In disclosing this to ADM, well-informed sources noted that this is a year later than was
intended until recently. However, it is well within the 2013-15 band for First
Pass approval set in the 2012 Defence Capability Plan (DCP), although this is
still two years later than the dates indicated in the 2009 DCP.
As forecast in the 2012 DCP, Initial Operational Capability
(IOC) for Phase 3 will now be reached sometime between 2017 and 2021, seven and
11 years respectively later than the date by which the entire project was
scheduled to have been completed when it was set up in 1996.
But even this date is open to conjecture, since the DCP states
that it will be further refined later in the proposal development process.
Acquisition cost has firmed from the 2009 estimate of $100-500
million to the middle of a $300-500 million band. Budgetary constraints would
suggest this figure is more likely to go down than up.
While individual health support capabilities will continue to
reside within the three services, Defence says the joint approach to the
development of JP2060 will enhance interoperability “and minimise duplication of
effort and resources that burden stovepiped service-based health support”.
The project has adopted a “whole of systems“ approach,
addressing preventative health, treatment, medical evacuation, health
information systems (command, control, communication, intelligence and information
management systems), and health service logistics.
A project definition study that was completed in 2003 led to the
acquisition under Phase 2A of portable ultrasound systems and medium-fidelity
mannequin systems. These purchases were completed in 2008.
Delivery of key items such as imaging systems,
Canadian-manufactured modular controlled-environment soft shelters, monitoring
instruments, forensic dentistry tools and logistics capabilities has now been
completed under Phase 2B.
A new digital imaging system prereleased in August 2010 to equip
an ADF medical task force assisting with flood relief in central Pakistan cut
patient waiting time from more than 10 minutes to two minutes, while continuing
to function in temperatures untenable for wet-film technology. Additional
systems were issued to the three services during the remainder of the year.
Enhancements to current capability will be progressively rolled
out over the next two years to complete Phase 2B. These will include portable
oxygen generators, aeromedical evacuation (AME) equipment suites to modernise
the current AME capability across Navy and Army, and medical waste incineration
to ensure more efficient compliance with state and territory legislation.
Phase 3 Next Generation Deployable Health Capability is intended
to take an integrated systems approach rather than dealing separately with each
of the five discrete health operating systems mentioned earlier.
Operational experience
Changes in the pattern of war trauma mean more of the seriously injured are
able to be resuscitated and returned to a level of health comparable to that
prior to injury. “Enabling this rate of survivability requires immediate first
aid, rapid evacuation with specialists providing en-route resuscitation and
early surgery in facilities with extensive clinical support capabilities,”
Defence states. “The project seeks to deliver this as an integrated network of
systems that is flexible, scalable and responsive.”
Clinical interventions will be delivered at the lowest possible
level as will improved trauma response, appropriate equipping of evacuation
assets for intransit care, and the modernisation and upgrade of surgical
capabilities with the ability to provide specialist care in the deployed environment.
Defence says it is currently working with the Australian Red
Cross Blood Service to deliver a frozen blood capability. This capability is
currently being used by coalition partners but has not been developed within Australia.
Additional technologies such as small, easily-deployed pathology testing units
are already being developed.
Other innovative technologies under development, as identified
by Wing Commander Michael Penman of the Directorate of Future Health Capability
in a presentation two years ago, include a noise-immune stethoscope to be used
in challenging environments such as helicopters, dried plasma with an extended
shelf life and temperature stability for use in cases of massive blood loss,
and portable oxygen generators utilising a thin, hot ceramic membrane with a
voltage applied that could eventually replace the standard “D” storage
cylinder.
Defence said it was unable to facilitate an interview with a
subject matter expert to obtain additional information on Phase 3, but ADM has elicited more details
from a variety of sources.
These have disclosed that Phase 3 has now been split into two
components, the first of which is the Health Clinical Component (HCC). This
involves the infrastructure of the deployable capability, ranging from modular
soft and hard shelters to sterilisation and laundry facilities and a wide range
of medical equipment.
The second component is the Health Knowledge Management (HKM)
system. This will encompass health intelligence on geographic and environmental
issues and information on deployed personnel ranging from patient tracking and
regulating to patient and clinical records, including imagery; case management;
the readiness and sustainability of deployed medical capabilities; notification
of trauma, deaths, serious illness and injury; and early assistance in the
detection of biological/chemical attacks.
The HKM component will also enhance the monitoring and control
of health materiel and supplies within a Joint Operations Area (JAO) given the
acknowledged deficiencies of existing logistics systems such as MILIS and
ROMAN.
IT details
As with other specialist software applications used on
operations, the HKM will be hosted on Defence’s Deployed Local Area Network (DLAN)
infrastructure. The dedicated communications to support the HKM are to be provided
by a number of other Defence projects, including JP2008 – Military Satellite Capability;
JP2072 – Battlefield Communications Systems (Land); and Sea 1442 – Maritime Communications
Modernisation.
A Request for Information (RFI) for the whole of Phase 3 was
released by Capability Development Group (CDG) in 2010. According to the
sources, this sought details of various capability elements on an individual basis.
Following an overseas study tour by representatives of both CDG and Joint
Health Command a second RFI was issued in 2011, this time seeking information from
companies interested in acting as a prime systems integrator.
Subsequently a third RFI limited to the HKM system was released in April, this time
by DMO’s Electronic Systems Division. Respondents were given four weeks to
identify potential COTS-based integrated eHealth solutions and their maturity, together
with systems integrators and vendors who have successfully delivered integrated
solutions for healthcare, “including other countries’ military organisations in
support of their deployed operations.”
“This means they’re going to have to come up with a requirements specification and
cost that has the potential to cause more delay to the overall program,” said one
industry source who spoke to ADM on the condition of anonymity.
“My feeling is Joint Health Command wants a complete and
integrated solution that includes the Clinical IT systems – this would deliver
a complete capability and make through-life support far easier to organise than
the piecemeal approach followed with Phase 2.”
The Concept of Operations (CONOPS) for Phase 3 includes an aspirational 10-1-2
hour metric. This involves controlling major haemorrhage and a secure airway within
10 minutes of injury; evacuation from the point of injury within one hour by
personnel capable of providing enroute advanced resuscitative care; and surgery
at hospital level care to commence not later than two hours following injury.
Patients requiring strategic evacuation would normally depart the area of
operations within 72 hours of admission; the most critically ill within 24
hours. The strategic AME is intended to be capable of moving up to eight
intensive care and 34 lower dependency patients per day at peak demand from
three separate theatres, sustained for five days.
The CONOPS segments the health facilities proposed by JP2060
Phase 3 into graduated levels of capability, with R1 resembling a traditional
regimental aid post capable of managing minor sick and injured personnel for
immediate return to duty, as well as casualty collection from the point of wounding
and preparation of casualties for evacuation to a higher level facility. R2
will add to R1 capabilities with triage, medical officer-led resuscitation and the
relevant support elements; basic imaging and field laboratory capability; and a
limited holding facility for the short term management of casualties until they
can be returned to duty or evacuated.
R2 Light Manoeuvre (R2LM) are light, highly mobile surgical facilities used
only for initial crisis intervention or war fighting deployments where direct
evacuation to R2E/3 facilities are impossible.
R2Es are small hospitals able to stabilise post-surgical cases for evacuation
out of theatre without first needing to evacuate to a Role 3. They will also
provide casualty decontamination facilities for chemical and biological warfare
casualties dependent on the operational risk assessment.
In addition to R2E capabilities, R3 centres will include
specialist neuro, maxillofacial and burns surgery, advanced and specialist
diagnostic capabilities to support clinical specialists, and major medical and
nursing specialities in internal medicine and neurology.
As well as surgical and medical intensive care capabilities
required for the seriously ill and injured, the holding capacity will be
sufficient to allow diagnosis, treatment and holding of those patients who can
receive adequate treatment and be returned to duty within the Joint Operations Area,
dependent on the theatre holding policy.
Contenders
Given that the Phase has yet to receive First Pass approval, industry is
understandably reluctant to discuss possible offerings.
However, Saab Technologies Australia confirmed to ADM it has responded to
all three RFIs. This is not surprising, given that its Swedish parent delivered
a sophisticated turnkey deployable medical care solution (MCS) to the Swedish
armed forces two years ago which was inspected in the course of the CDG/Joint
Health Command study tour.
According to Saab marketing material, the MCS can be
mission-tailored according to tasks and climatic conditions. Each tent is self-contained
and has common wiring and connectivity with other modules, enabling the
capability to be scaled and adapted appropriately for whatever the situation
requires.
Medical equipment is all COTS to facilitate support, and the
company says it can provide end-to-end backing for the MCS including equipment,
operation and maintenance services whenever it is needed and in any location.