Capabilities: Australia defers JSF in line with US | ADM June 2012
By Nigel Pittaway | Melbourne | 25 June 2012
Defence Minister Stephen Smith’s
announcement in May that the Government will delay the purchase of 12 Lockheed
Martin Joint Strike Fighters by two years did not come as any great surprise.
Given the pressures
it faces balancing the budget, the reported $1.6 billion savings from forward
estimates is a significant portion of the $5.45 billion of Defence savings the
Gillard Government flagged in the lead up to the budget. The budget also flags
the subsequent deferral of the next batch of 58 aircraft, saving a further $700
million.
Minister Smith also indicated that the delay broadly
aligns Australia’s Joint strike Fighter acquisition program with the US Air
Force, which has deferred 179 of its own aircraft from earlier Low Rate Initial
Production (LRIP) batches.
The deferral comes as the New Air Combat Capability
(NACC) Project Office reviews the impact it will have on capability and whether
there will be a need to mitigate any gap by either extending the Planned Withdrawal
Date of the ‘Classic’ Hornet fleet or, as Smith has previously flagged, buying
a further tranche of Super Hornets in the interim.
With the Government’s mind on extracting savings from
the Defence budget, there are many who now think a revised withdrawal of the
Classic Hornet is the more likely of the two scenarios. Australia indicated it
would acquire an initial tranche of 14 F-35As in 2009, at a cost of $3.2
billion, and is committed to receiving the first two aircraft, from LRIP Batch
6, in 2014. The other 12 were to come from LRIP batches 8 & 9 from 2016,
but the new production profile has yet to be worked out.
Under the schedule revised in 2010, the first two
aircraft will cost Australia around $130 million (at 2012 prices and using an
exchange rate of 1.03). The average cost over the initial 14 would have been
around $110 million (Unit Recurring Flyaway cost), using the same metric, but this
will now depend upon the new delivery profile.
Assuming no further cost increases, always a risky
business where the JSF is concerned, the average unit cost of this first batch
should now be less, as 12 aircraft will be built in later LRIP batches.
Speaking from the US, where he is attending the JSF
Chief Executive Officer’s conference, Air Vice Marshal Kym Osley, head of the
NACC program, said the planned review will determine the acquisition program and what further measures will be required to
ensure a robust air combat capability is maintained in the transition to the
F-35A.
“The Minister and Defence consider the deferral
prudent, given the associated risk with schedule, and the Minister has clearly given
us direction that we are to report back to Government later this year with a plan
that covers a number of things,” he said. “The key thing will be the potential for
any air combat capability gap.”
AVM Osley says the report will compare the capability
required to match regional capabilities and outline options for the ramp-up of
the JSF capability to meet a Government agreed Initial Operating Capability
date. He says the Hornet fleet has only just finished the Hornet Upgrade
program and the Planned Withdrawal Date (PWD) may be able to be rescheduled.
“At this point in time it’s a reasonably robust fleet,
so we’ll look at what flexibility we have in the PWD,” he said. “But we’ll also
consider other options, such as the Super Hornet.”
The US Government revised the JSF System Design and
Development schedule in 2010, following Technical and Integrated Baseline
Reviews, after identifying technical risk and concurrency issues – specifically
the ramp up of production while flight test was still only in its early stages.
This restructure cost the US taxpayer US$7.4 billion,
though no additional money was levied from any of the partner nations, and has
delayed IOC for the USAF by two years to either late 2018 or early 2019. The
concurrent deferral of 179 of its own aircraft has also contributed to US
Government efforts to reign in the domestic budget deficit. The Australian deferral
of two years puts the RAAF program broadly into line with the USAF. Originally due to be
delivered by 2017, the next 12 aircraft, after the two in 2014, will now be
delivered by 2019, though IOC and FOC dates are not yet clear.
“The ramp up that we need year-by-year is yet to be
determined,” explained AVM Osley. “We will also have to determine how many
pilots we will need to meet the IOC timeframe, so we end up with the right number
to meet the IOC requirement.”
Pilots for all JSF operators will be trained at an
Integrated Training Centre (ITC) in the US, but the system requires each nation
to contribute aircraft to the process, in order to gain training credits.
Australia’s first two aircraft will come off the Fort
Worth production line sometime in 2014, but will then have to undergo a substantial
airworthiness and certification process, which will take several months. From
there they will go to the ITC, most likely to be at Luke Air Force Base in
Arizona, to begin earning the required credits. The first RAAF pilots will
arrive at the ITC in either late 2014 or early 2015.
“Some of the initial Australian pilots will train on
the aircraft in preparation for our own Operational Test and Evaluation,” said AVM
Osley. “Others will form our initial cadre of Qualified Flying Instructors
within the ITC.”
Four aircraft will be delivered to Australia to begin
OT&E, leaving the remaining 10 within the ITC to generate training credit for
subsequent batches of pilots. After IOC, the training aircraft will be transferred
to Australia, at which time the local training unit will begin the stand-up
process. As for the future of the test and development program, AVM Osley says
he sees software as being one of the major challenges.
“The F-35s capability advantage is in the way it
synthesises information and fuses it together. No other platform has done this
to the same level, not even the F-22A,” he asserts. “I do expect some delays, they
will reach some stumbling blocks with software development and there will be
some software they will have to delay to later builds.”
As a measure of confidence however, AVM Osley points
to recent exercises where the various sensors have been employed, albeit on
other platforms and not integrated into one aircraft, which have achieved outstanding
results.
“Software development is a key metric that I monitor
almost every day in the program office and it will be a key determinate of when
the real capabilities are realised on the aircraft,” he concluded. “There is a
degree of schedule flexibility, but we’ll want to see Lockheed Martin setting
and meeting milestones, then demonstrating them in flight test.”