Work on NIOA’s new state of the art facility is progressing well, with much of the administration and firing range sections now standing with work on interior floors and ceilings well underway.
The bold angular architecture of the office can now clearly be seen from the roadway and the massive warehouse walls are scheduled to be lifted in the next few weeks. Despite rain delays early in the project, final completion is still on track for the first quarter of 2014.
Facility Highlights:
- Over 5000m2 of high security DISP accredited warehousing space
- Leupold optics repair centre and custom shop
- 100m indoor test fire range for up to 40mm cannon
- Heavy grade weapons repair facility for all commercial and military firearms
- 200 seat training auditorium
- Integrated logistics capability with ready airside access