A
high precision Enerpac SyncHoist
system has been successfully deployed by heavy lift and transport specialists
Universal Cranes to ensure optimum accuracy and safety in the hoisting and
positioning of key components of one of the largest ships ever built for the
Royal Australian Navy.
Universal Cranes integrated the
system with a 600 tonne crawler crane as part of the project management and
engineering for the consolidation of steel blocks of between 164-300 tonnes on
the deck of the first of the Landing
Helicopter Dock (LHD) vessels being built by BAE Systems Australia.
The
four steel blocks, with variable centres of gravity, will become the operating control towers on
the flight deck of the Canberra class LHD, one of two 28,000 tonne LHD vessels
that will come into service in 2014 (HMAS
Canberra) and 2015 (HMAS Adelaide)
respectively.
The
Enerpac SyncHoist system involved in construction of the Canberra offers load
manoeuvring vertically and horizontally using one crane, being employed in this
application to align the block so the crane could lower it.
Employing
intelligent hydraulics to monitor and guide compact but powerful 700 bar
double-acting push-pull cylinders integrated into four lifting points above
loads, the SyncHoist SLS system can be used for pre-programed positioning,
tilting and aligning of loads and for counterweighting and determining their
centre of gravity.
Universal Cranes heavy lift engineer Nick Morris said that, because of the
size of the vessel, the use of traditional craneage and dry dock option was not
feasible.
The Demag CC2800-1 crawler crane was rigged with a 72m
Main Boom in Superlift Lift (SSL), and positioned to work from the Nelson Pier
adjacent to the moored LHD Vessel.
“The grillage, weighing approximately 600 tonne,
allowed the crane to be positioned on the pier structure with loads effectively
transferred directly to lower piles. The
grillage was then relocated by the crane in preparation for each sequential
lift,” Morris said.
Universal Cranes purchased a 440t Enerpac Synchronised
Hoisting System specifically for the LHD Project. The system, comprising of four hydraulic
cylinders each capable of 110t and offering a stroke of 1500mm, can be
installed within a rigging arrangement in tension providing an overall capacity
of 440 tonnes.
Universal Cranes’ contract also involved engineering
and project management in the fabrication of a 330t purpose designed lifting
frame for the project.
This lifting frame was adapted with specific sling lengths
for each specific block.